The job

A restaurant’s prep sinks were draining slowly, and the floor drain backed up during dinner service. The grease interceptor was overdue for a pump-out, and the yearly backflow test was due the same week.

What we did

Two technicians arrived at 6 a.m., before the kitchen opened. They pumped out the grease interceptor, scraped the walls, and checked the baffles and outlet. The kitchen line was then jetted from the sinks to the interceptor to clear the built-up grease. Last, the backflow preventer on the main supply was tested and tagged, and the report was filed with the water authority.

The result

The sinks and floor drain ran freely for lunch service. The restaurant moved to a pump-out every eight weeks, with the backflow test booked on the same visit each year.

What the customer said
“Done before lunch prep started, and the test report went straight to the water authority.”

Ahmed F. · Restaurant owner, Old Mill

Closed · Sep 24, 2026

  • Visit booked before opening, kitchen closed
  • Grease interceptor pumped out and scraped
  • Baffles and outlet checked for damage
  • Kitchen line jetted from the sinks to the interceptor
  • Backflow preventer tested and tagged
  • Test report filed with the water authority
  • Technicians: 2
  • Time on site: 3 h 30
  • Area: Old Mill

Job total$640

Fixed price per visit, test report included

Get a price for a job like thisSee this service

Have a job like these?

Tell us what is leaking, blocked, or not heating. You get a price before any work starts.